Adjusting procedures on an idle generator with a rotor rolled out from a stator:
use a TV endoscope to evaluate the stator winding condition in the generator;
use a TV endoscope to evaluate the rotor winding condition in the generator;
carry out an ultrasonic inspection of the active steel in the stator;
check a condition of the structural component;
measure the parameters (R60/R15) of the stator winding insulation in the generator, and determine the required test voltage magnitudes (50 Hz test voltage and rectified test voltage);
use a rectified test voltage to test the stator winding insulation and to determine the nonlinearity factor of an insulation leakage current;
use an increased test voltage (50 Hz) to test the stator winding insulation;
measure the parameters of the rotor winding insulation;
measure the rotor AC resistance;
measure the stator winding DC resistance;
carry out a chromatographic analysis of hydrogen from the generator case;
to provide fair automated inspection of the condition of cores in high-power electric machines, before and after repair, several times scan a stator bore after outage for repair (with a rotor rolled out) and after completion of a repair, to check its quality.
Adjusting procedures on an idle generator with a rotor placed into a stator and with closed end shields on a generator:
apply an increased AC voltage to measure the insulation resistance and to carry out a check test of the stator winding insulation;
measure the parameters of the rotor winding insulation;
measure the rotor AC resistance.
Adjusting procedures the rotating electric machine:
determine the short-circuit characteristics;
determine the no-load characteristics;
measure the residual voltage on the generator lead-outs.
In accordance with the tests results, the generator condition report is issued.
Starting-up and adjusting procedures for the generator exciting systems commissioning:
Starting-up and adjusting procedures on a high-voltage side:
primary equipment (switch etc.);
control circuits, relay protection circuits and automatic equipment for the generator alarm systems;
generator synchronization systems.
Starting-up and adjusting procedures on a low-voltage side:
control, protection and automatic operation circuits for motors (operating the circulation pumps, oil pumps etc.);
power assemblies equipment (PR-85, RTZO-88);
balance-of-plant switchgear (RUSN) 0.4 kV.
Starting-up and adjusting procedures for the power transformers commissioning: full range of works stipulated by the “Electric Equipment Tests Procedures and Schedules” Regulation.
Preparation of instructions: operation instructions for newly commissioned equipment, including the generator, exciting system, transformers, brush contact equipment (if applicable), motors, relay protection circuits and automatic equipment for standby lead-ins, generator protection microprocessor-controlled terminals, generator rotor ground fault protection kits, manual and automatic synchronization devices, power equipment switchgear (KRU) 6-10 kV, balance-of-plant switchgear (RUSN) 0.4 kV, distribution devices (RU) 110 kV, electromagnetic polarized relays; instructions for elimination of faults of electric equipment; fire safety instructions.