Reference of JSC "Power Machines"

Branch in Greece

 

Dear Sir,

As you are aware OJSC "Belenergoremnaladka" (BERN) and OJSC "Power machines" have undertaken works for upgrading and general overhaul of turbine K-300-170, Unit №3 TPP "Aghios Dimitrios" in the frame of the Contract Agreement №071413/052147-0736/17.01.2008 in Republic of Greece, in 2008.

There were implemented the upgrading of steam path of the turbine besides of routine repair works. It was changed the automatic control governor system, installed sliding plates, Siemens' production, in the sliding plane of bearings' houses and foundation frames.

During execution of works at site there were repeatedly arisen technical problems which owing to the professionalism and well-organized works of BERN's and Power machines' specialists have been settled down successfully.

we would like to express our gratitude to OJSC "Belenergoremnaladka" for faithfull works and concern in implementation of the project and hope for further fruitful and mutual benefit collaboration with your Company in realization of other energy projects.

 

With best regards,

 

Director of Power Machines

Branch in Greece                                                                                                                                 I. Bakarinov

 

 

Reference  of Limited Company «Energotechmash»

Limited Company «Energotechmash» expresses its gratitude for excellent joint work on replacing of superheater and reconstruction of blow case СРКА-1750 st. №1.

Employees of your enterprise on conditions of tight schedule and difficult situation have shown high professional qualities, leader skills, abilities to take right administrative decisions.

Your experts have developed effective technical decisions on implementation of the project that conform industrial safety principles of the Russian Federation, comply with accident prevention procedures.

We hope for further cooperation!

 

Director                                                                                                                                                 V.V. Gorbunov

 

 

Reference of JSC «Lietemas»

 

In May-August, 2009 the employees of JSC «Belenergoremnaladka» executed total overhaul works on turboset T-100-130 st. №2 and turbine-generator ТВФ-120-2 st. №2 of Kaunas Power Station.

We would like to underline high level of work organization, professional and technical experience of the employees of JSC «Belenergoremnaladka».

We express our gratitude for high quality of installation and adjustment works fulfilled in due time.

We hope for further effective co-operation of our companies.

 

General Director                                                                                                                                 Zenonas Svetlikauskas

 

 

Reference of «Energoproekt»-«Tsentrenergoproekt»

 

September, 2007 – February, 2009 JSC «Belenergoremnaladka» fulfilled installation and adjustment works at first line thermal and mechanical equipment of thermal power plant at Moscow International Business Center «Moskwa-city» in Moscow.

Experts of JSC «Belenergoremnaladka» executed works at thermal and mechanical equipment of 120 MW CCGT unit, they worked mostly with equipment of companies «ALSTOM» and «SIEMENS». They fulfilled works on analyses of Pi-diagrams and project engineering documentation package for thermal and mechanical issues of the project, developed decisions and recommendations to the administration for eliminating drawbacks discovered. They supervised equipment installation and eliminated installation drawbacks discovered, diagnosed for defects of the equipment and developed recommendations for their clearings. Participation in commissioning and testing assembly equipment installed.

The works entrusted to JSC «Belenergoremnaladka» are fulfilled at high technical and professional level. All technical problems that arose at TPS construction were solved timely and in a quality manner by experts of JSC «Belenergoremnaladka». All these ensured prompt handing over of works at first line equipment of thermal power plant at Moscow International Business Center «Moskwa-city» to the Client and its commissioning in spite of tight schedule.

We express our gratitude for fruitful participation of employees from your enterprisein construction of first line TPS at Moscow International Business Center «Moskwa-city» and we hope for further cooperation in future projects.

 

Yours sincerely,

 

Deputy Administration Head

Of MIBC «Moskwa-city» constructions                                                                                           S.V. Rumyantsev

 

 

Comment of Belarusian gas processing plant RUE «Production association «Belorusnefts»

 

At nonoperational overhaul of the plant conducted in April, employees of your enterprise fulfilled works on preventive inspection of digital protection of 110/6 KW substations «Belarusian gas processing plant» that are based on terminals: REL-511 v.2.3; SPAC 801-01; REB 103; RET 316 v.6.2а; SPAU 341; SACO 64D4 produced at «ABB».

High qualification and good experience of experts of JSC «Belenergoremnaladka», good organization and advanced equipment ensured prompt and excellent conduction of works.

Employees of JSC «Belenergoremnaladka» that executed works on Relay Protection and Automatic Equipment maintenance have high qualifications, deep knowledge in modern power engineering, and huge experience in handling microprocessor-based terminals.

Based on the results of work, detailed technical papers are given in accordance with obligations of contract. Your experts also continue maintaining conducted works, providing consultations and recommendations for operations department of the enterprise.

We express our appreciation of work accomplished and hope for further cooperation.

 

Chief Engineer                                                                                                                                A.V. Luchenok